A coastal concordat for England: implementation document (updated: December 2019)
Updated 23 June 2021
1. Introduction
This document is for use by staff in regulatory and advisory bodies that have adopted the concordat principles (defined as ‘concordat bodies’ for the purpose of this document).
This document will also be of interest to applicants and other regulators/advisors as it sets out what they can expect from concordat bodies where applications fall within the scope of the concordat, and highlights the responsibilities of applicants in that context.
As the concordat is implemented, lessons learned will be fed back into future versions of this document.
This document should be read in conjunction with the coastal concordat, which sets out the detail of each principle.
2. First point of entry
2.1 Definition
Where an application or proposal is screened in as a concordat project, the organisation first approached should identify an officer to assume the role of the first point of entry into the regulatory system if:
-
the project is within the remit of their organisation. If it is outside of the remit of the officer’s organisation, the officer should consider whether the application falls within the remit of another concordat body and provide the applicant with appropriate details to enable them to make contact
-
the application or application enquiry has come directly from the applicant and it is confirmed they have not contacted another concordat body. If notification of an enquiry comes through from one of the other concordat bodies, or the officer finds that one of the concordat bodies has already been contacted, the officer should confirm that the other body has assumed the role of the first point of entry
2.2 Identifying coastal concordat projects – concordat screening
When acting as first point of entry, officers in concordat bodies should screen all applications processed from an applicant to determine whether the concordat principles should be applied. Application enquiries which form formal pre-application requests should also be screened. Organisations will still reply to the application or application enquiry within their existing statutory timescales.
The concordat should be implemented if all points on the following screening checklist apply:
- the development is in a participating Local Authority area[footnote 1]
- the footprint of the proposed development (and any ancillary infrastructure) is both terrestrial and has elements that fall below Mean High Water Springs[footnote 2] within an estuary or on the coast
- the development requires multiple consents including both a marine licence and a planning permission
- there are no other co-ordination mechanisms already in place, for example applications for Nationally Significant Infrastructure Projects (NSIPs) under the Planning Act 2008 or applications under the Transport and Works Act 1992
For projects that meet the criteria for the coastal concordat, but are in areas where the local authority has not yet implemented the concordat, officers should apply the concordat principles in partnership with the other concordat bodies as far as possible, as part of current joint working arrangements. In these cases, officers should explain the benefits of the coastal concordat approach to the local authority and encourage them to contact Defra about adopting the concordat via email to [email protected]. While the local authority and concordat bodies may wish to use the project to test the approach in the area, officers should use the opportunity to encourage formal participation in the future.
2.3 Signposting
The role of the first point of entry officer will be to gather information from the applicant about the project including at least:
- the applicant’s name and contact details
- the proposed location of the works, timescale and their nature
- whether any other regulatory body or advisor has been contacted
The officer will then initiate the concordat implementation process set out in Figure 1 and described in more detail below.
The first point of entry officer should signpost the applicant to those relevant concordat bodies that have not already been contacted, highlighting that the applicant may need to secure a consent, licence or permission from them, encouraging parallel tracking where possible. Officers acting as the first point of entry should not attempt to identify which consents will be required – this will be the responsibility of individual concordat bodies once contacted. Where relevant, the body acting as the first point of entry should also inform the applicant of the concordat. It remains the responsibility of the applicant to obtain all necessary consents.
2.4 Regulatory remits of organisations applying the concordat
As a guide, the regulatory remits of the relevant concordat bodies are outlined below (this is not exhaustive and if an officer is in any doubt, they should signpost the applicant to the relevant body). Further information on the most common types of consents, licences and permissions issued by the concordat bodies is available in Annex A.
Local Planning Authority / National Park (LPA)
Any works above Mean Low Water.
Marine Management Organisation (MMO)
-
Any licensable activity below the Mean High Water Springs mark in tidal rivers, estuaries and on the coast
-
Any works that require harbour revision orders or harbour empowerment orders
-
Any activity below the High Water Mark prohibited under wildlife legislation such as killing or taking certain protected species to prevent problems, carrying out surveys or conservation work, disturbing or damaging the habitat of certain strictly protected species, possessing or keeping certain wildlife
-
Harbour re-organisation schemes
Environment Agency (EA)
-
Any works in, under or over most estuaries, works within 16 metres of the tidal main river and within 16 metres of any flood defence structure or likely to affect beaches, promenades or sea defences
-
Land based discharges, any ship breaking, or keeping or disposing of radioactive sources out to 12 nautical miles
-
Any building or changes to industrial plants, any waste activities on land or shipments of waste or radioactive material
-
Any abstractions, impoundment or water transfer in any natural or artificial tidal river, stream or other watercourse, reservoir, dock, channel, creek, bay, estuary or arm of the sea
Natural England (NE)
-
Consents and assents to owners/occupiers of SSSIs
-
Licensing of activities otherwise prohibited under wildlife legislation for the killing, taking or disturbance of terrestrial European and UK protected species or for damage or disturbance to their habitats
-
Responsible for advising on the conclusion(s) of Habitat Regulations Assessments
Department for Transport
-
Transport and Works Act (TWA) Order for large-scale transport infrastructure, including railways, trams, bridges, piers and tunnels (outside concordat). Read a brief guide to TWA orders
-
Statutory consents in local legislation, except those related to infrastructure (see MMO), which may include the sale of harbour authority land
2.5 Contacting relevant concordat bodies
The contact details for relevant concordat bodies are set out below. The roles and responsibilities of the concordat bodies are set out above and also in Annex A.
Find out about call charges at www.gov.uk/call-charges.
Marine Management Organisation
Email: [email protected]
Telephone: 0300 123 1032
Natural England
Email: [email protected]
Telephone: 0300 060 3900
Environment Agency
Email: [email protected]
Telephone: 03708 506 506
Local Planning Authorities/National Park Authorities
These adopters should only be contacted if the proposed development falls within their geographical area. For Local Planning Authorities/National Park Authorities that have signed up to the concordat principles please see the list available at www.gov.uk/government/publications/a-coastal-concordat-for-england
Department for Transport
Transport Works Act Orders
Email: [email protected]
Telephone: 020 7944 2474
Consents under local or private Acts
Email: [email protected]
Telephone: 030 0330 3000
3. Coastal Concordat working
3.1 Initiating discussions
The most appropriate body will normally lead on initiating early discussions (e.g. face-to-face meeting, teleconference or videoconference) between relevant concordat bodies where necessary. It is likely that this will be most necessary for projects that may require an Environmental Impact Assessment (EIA) and/or Habitats Regulations Assessment (HRA). These discussions should cover at least:
- ensuring a collective understanding of the project between concordat bodies
- discussion of which concordat bodies should be involved. Where appropriate this should also pick up any non-concordat bodies such as Historic England, Crown Estate, harbour authorities and the Inshore Fisheries and Conservation Authorities
- ensuring a collective understanding of the developer’s timescales for the project, outline of the statutory response requirements of each concordat body, discussion of roles and contacts for the project
- how and where chargeable services apply
- whether the proposal might require an EIA and/or HRA
- the lead authority for EIA and HRA (where the project requires this)
- whether there may be opportunities to dispense with or defer regulatory responsibilities and, if, so which bodies will pursue that
- arrangements for contacting the applicant to outline the conclusions of these discussions to enable further pre-application discussions with the applicant
To ensure transparency is maintained throughout the consenting process each concordat body should put in place mechanisms to ensure that other concordat bodies are aware of projects as they progress, e.g. through copying others in on correspondence where appropriate.
3.2 Roles and responsibilities of lead authorities for Habitats Regulatory Assessment/Environmental Impact Assessment
The identification of the lead coordinating authority for HRA/EIA and decisions on their roles and responsibilities should be determined using existing DLUHC and Defra guidance and the concordat itself, as appropriate.
Regulation 10 of the Marine Works (Environmental Impact Assessment) Regulations 2007 (as amended) (MWR) sets out the circumstances in which the MMO may determine that EIA is not required under the MWR, for example where a sufficient assessment is carried out by another consenting authority.
Therefore, if it is determined that the main aspects of a project, which requires EIA under both the MWR and Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (TCPR), are terrestrial, the MMO should defer the assessment of compliance with the EIA Directive, or domestic law that gave effect to the requirements of the Directive, to the LPA, provided that any marine aspects are assessed to their satisfaction.
Similar provision is not given under the TCPR. In the absence of such provision, if it is determined that the main aspects of a project which requires EIA under both the MWR and TCPR are marine, the administrative lead for the EIA process should be the MMO. A consolidated process should be put in place that meets the requirements of both sets of regulations.
3.3 Dispensing with consents
Concordat bodies should explore opportunities for dispensing or deferring regulatory responsibilities where they are legally possible and appropriate. One option for doing this is under sections 82 and 84 of the Marine and Coastal Access Act, where the EA can dispense with the requirement for a flood risk activity permit where they consider it appropriate to do so. This can be carried out by service of a Notice by the EA where a marine licence has been applied for and the EA are satisfied with the conditions that will be attached to it. EA officers should determine this on a case-by-case basis using their internal guidance ‘373_14 Flood and Coastal Risk Management: Flood Defence Consents and Marine Licensing’.
3.4 Certainty on Evidence Requirements
The lead authority for EIA and/or HRA will also encourage the applicant to undertake early engagement with all regulators to identify common evidence requirements across different consenting regimes, so that wherever possible the information submitted should be sufficient for both the planning permission and marine licence approvals and may inform relevant consents, licences and permissions.
3.5 Coordinated Advice
Each concordat body will be individually responsible for ensuring that they provide coordinated advice from across their respective organisation within agreed timescales throughout the application process.
3.6 Conditions and the discharge of planning conditions
The principles of the coastal concordat should also be applied both when drafting the conditions of a consent and to the discharge of those conditions. Concordat bodies should work together to ensure that they are co-ordinated when developing and discharging conditions in order to minimise overlaps and duplications of information requirements.
In drafting conditions, concordat bodies should work together to ensure that conditions across the different consents are drafted consistently and coherently. There should be no duplication of control across the consents for concordat bodies as such planning conditions may not meet the test of necessity.
Concordat bodies should also ensure that common evidence requirements are identified wherever possible during the discharge of conditions stage, for example where there are monitoring and reporting requirements.
3.7 Responsibility for securing consents, licences and permissions
Through concordat working, concordat bodies will make every effort to ensure that developers are aware as early as possible of the full range of consents, licences and permissions that may be applicable to individual developments. Concordat bodies should encourage developers to engage with them via pre-application services they offer. It remains the responsibility of the applicant to obtain all necessary consents.
4. Example Scenarios
To further illustrate how the concordat might be applied in practice a number of example scenarios are set out in below.
4.1 Example 1
Applicant A approaches the MMO with a proposal for a marina at the mouth of an estuary adjacent to a Marine Protected Area. The marina consists of a number of berths below Mean High Water Springs, and a small clubhouse on some brownfield land connected to the jetties by a walkway over the flood defence. The MMO screens this in as a concordat project, and, assuming the role of the first point of contact, ensures the applicant is aware that they will need to speak to EA and NE, as well as the LPA.
The first point of contact (in this case the MMO) encourages the applicant to provide to each relevant concordat supporter (MMO, EA, NE and LPA) the application reference and contact details for each application made to the other relevant adopters.
The MMO (as the most appropriate body in this case) initiates a telecom/meeting of the four organisations to discuss the project and EIA and HRA requirements. The supporting bodies consider that the project is likely to require an EIA and HRA. They decide that as the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 do not enable the LPA to formally defer to the MMO, the MMO should be appointed administrative lead for coordinating EIA, and that the MMO should also coordinate any potential HRA requirements. The group identify that the applicant may need to speak to the Crown Estate and the Harbour Authority for the estuary. The EA decides to retain their ability to issue a Flood Risk Activity Permit due to the potential impact on the flood defence. The group decide that the MMO will contact the applicant to explain their discussion and encourage them to begin discussions with the LPA, MMO, NE and EA in order to continue the pre-application process. This will confirm the need for EIA and/or HRA and identify any common evidence requirements (e.g. for the EIA for MMO & the LPA, the Flood Risk Activity Permit for the EA and the Wildlife Licence for NE/MMO). The applicant completes their environmental assessments and proceeds with their applications in parallel.
4.2 Example 2
Applicant B approaches the LPA with a proposal to build a house on the coast. In order to build on the site they also need to carry out repairs to the flood embankment, which is within the site. The Local Authority identifies the project as falling within the scope of the concordat (screening it in), as the repairs to the flood embankment will involve works below mean high water, falling within the remit of the MMO and the EA. The LPA assumes the role of first point of entry and advises the applicant that they will need to speak to the MMO and EA.
The first point of contact (in this case the LPA), encourages the applicant to provide to each of the relevant concordat adopters (LPA, MMO and EA) the application reference and contact details for each application made to the other relevant adopters.
The LPA sets up a meeting/teleconference with all relevant parties to discuss working arrangements. As the activities related to the flood embankment are small scale and have low environmental risk, it is identified during discussions that the proposal is likely to fall outside the scope of an EIA and HRA; however, it is thought that the Crown Estate would need to be involved in the project as permission will be needed to build on the sea bed.
The works to the flood embankment could affect the stability of the wall and therefore the EA decides to retain its ability to issue a flood risk activity permit. This discussion is fed back to the applicant by the LPA. The applicant discusses the site investigations for the embankment repairs with the LPA, EA and MMO, so that the evidence requirements for the planning application, the flood risk activity permit and the marine licence are all met and the applicant continues with the application process.
4.3 Example 3
Applicant C approaches the EA with a proposal to change the use of an industrial plant at the top of an estuary, modifying an old outfall to discharge waste effluent from the site from a discharge point in the middle of the river. The EA screens this in as a concordat project as the works to fit new diffusers to the old outfall will be below mean high water. The EA assumes the role of first point of contact and recommends that the applicant contact the MMO and the Local Authority, as the applicant will also need to obtain permission from them.
The first point of contact (in this case the EA), encourages the applicant to provide to each relevant concordat adopter (MMO, EA and LPA) the application reference and contact details for each application made to the other relevant adopters.
The EA initiates a meeting/teleconference between the EA, MMO and Local Authority to discuss the project. They decide that the Harbour Authority would also need to be involved due to the possible navigational impact. Although the works to the outfall are within a Main River and would require a flood risk activity permit, the EA advises that the works are unlikely to impact on flood risk and therefore dispense with the requirement for a permit where a marine licence is in place.
An EIA and HRA would not be required, however the EA, LPA and MMO require evidence gathering around potential thermal impact on the river in support of the application. This is fed back to the applicant by the EA and the applicant arranges a meeting between all parties to discuss the required modelling for all the permissions, licences and permit variations required. The applicant proceeds with the process, parallel tracking the planning permission, environmental permit and the marine licence together where possible.
5. Annex A: Examples of the most common consents, licences and permissions issued by concordat bodies
5.1 Examples of regulation encountered in the marine environment
Examples of Local Authority regulations
Local Authority regulation | Indicative determination time |
---|---|
Planning Permission | Most within eight weeks, unless major - time limit extended to 13 weeks or 16 weeks if EIA required. Extension can be agreed between LPA and applicant |
Listed Building Consent | Most within eight weeks, unless major –time limit extended to 13 weeks |
Examples of Marine Management Organisation regulations
Marine Management Organisation regulation | Indicative determination time |
---|---|
Marine licence | MMO aim to issue 90% of marine licence decisions within 13 weeks. This does not include time on hold awaiting information. Each application is different and the detail of the activity will affect this |
Electricity Act Section 36 consents | MMO aim to issue 90% of marine licence decisions within 13 weeks. This does not include time on hold awaiting information. Each application is different and the detail of the activity will affect this |
Offshore Renewable Energy Installation Safety zone consents | MMO aim to issue 90% of marine licence decisions within 13 weeks. This does not include time on hold awaiting information. Each application is different and the detail of the activity will affect this |
Marine Wildlife Licence (UK or European marine protected species) | Around 6 weeks |
Harbour Empowerment Orders | Varies depending on the detail of the application, average time issue is 12 months |
Harbour Revision Orders | Varies depending on the detail of the application, average time issue is 12 months |
Examples of Department for Transport regulations
Department for Transport regulation | Determination time |
---|---|
Transport and Works Act Orders | Varies in accordance with nature of application and the duration of any public inquiry |
Consents under local harbour authority Acts | Dependent on nature of request and whether other bodies need to be consulted about consent – guide of 3-6 months |
Examples of Environment Agency regulations
Environment Agency regulation | Indicative determination time |
---|---|
Flood Risk Activity Permit | Two months |
Environmental Permit | Standard or bespoke permit application usually up to 13 weeks; exemption usually 5 days |
Abstraction/Transfer/Impoundment Licence | Usually 28 days for temporary licence, all other licence applications within 4 months |
Radioactive Substances Regulations Permit | Up to 4 months |
International Waste Shipments & Radioactive Shipments | Usually 30 days (3 months for radioactive shipments) |
Waste Regulation – Carriers/Broker/Dealer WEEE/Packaging/Hazardous/PCBs/Waste Battery Facility etc | Registration/Approval |
Fish introduction or removal consent; consent or authorisation for use of nets, traps etc. | Usually up to 10 working days, but may take up to 20 if in a protected area or requires fish health check |
Agreement to use herbicides in or near water | Usually two weeks. If consultation with NE required, they have 28 days to respond |
Carbon Reduction Commitment & Climate Change Agreements, EU Emissions Trading Scheme Permits | Registration |
Harbour and mooring charges - Rye and Lydney Harbours; Pilotage (Rye only) | As received |
Examples of Natural England regulations
Natural England regulation | Determination time |
---|---|
Wildlife and Countryside Act (Sec 28E) – SSSI consents (to owners/occupiers for their own operations) | |
Note: S28E does not apply in cases where the operation is authorised by planning permission or another consenting regime and the requirements of S28I (below) have been met. | Within 28 days in most cases but statute allows up to four months if required |
Wildlife and Countryside Act (Sec 28H) – SSSI assents (to public bodies for their own operations) | Within 28 days by statute |
Wildlife and Countryside Act (Sec 28I) – SSSI advice (to public bodies in relation to their permitting activities to third parties) | Within 28 days by statute |
Conservation of Habitats and Species Regulations 2017 (Reg 24 – European site consents (to owners/occupiers for their own operations). Essentially replicates W&CA Sec 28E (above) for European sites ie SPAs and SACs | Within 28 days in most cases but statute allows up to four months if required |
Conservation of Habitats and Species Regulations 2017 (Reg 55) – licences permitting the disturbance, killing or taking of European protected species or damage/disturbance to their habitats. For development-related purposes, Natural England carries out this licensing role on behalf of the Secretary of State. | Performance standard: 30 working days |
-
See list at www.gov.uk/government/publications/a-coastal-concordat-for-england ↩
-
Please refer to Ordnance Survey data in the first instance. For marginal cases please contact the MMO. ↩