Keadby II, gas fired generating station: variation to Section 36 consent, Electricity Act 1989

Decision by the Secretary of State on an application to vary a Section 36 consent for a combined gas fired generating station.

Documents

Keadby II S36C variation: Consent

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Keadby II S36C variation: Corrected version of the varied Section 36 Consent, 13 March 2019

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

Decision by the Secretary of State on an application to vary a Section 36 consent for a combined gas fired generating station.

Date of decision

1 March 2019

Company / location

Keadby Developments Limited
Keadby
North Lincolnshire

Combined gas fired generating station (CCGT) / s36C Electricity Act 1989

Maximum output

910MW