Agreement holder's guide: Protection and Infrastructure grants 2023
Updated 5 August 2024
Applies to England
Read this guidance if your agreement started between 5 January and 31 December 2023.
A Countryside Stewardship (CS) Agreement comprises:
- the scheme Terms and Conditions
- an Agreement Document (which sets out specific details for the Agreement Holder
- the supplementary documents referred to in the Agreement Document
The Terms and Conditions (Annex 1) refer to the mandatory elements of this guide that Agreement Holders must comply with.
CS Protection and Infrastructure grants are for a maximum of 3 years.
The Agreement will usually start from the first day of the following calendar month after you have accepted the agreement offer. The exact start date of the agreement will be set out in the Agreement Document.
Mandatory sections you must comply with:
- section 5: Protection and Infrastructure requirements and procedures
- section 6: Manage your Protection and Infrastructure grant Agreement
5. Protection and Infrastructure requirements and procedures
You must read and meet the requirements detailed in this section as these are mandatory for all CS Protection and Infrastructure grant Agreement Holders.
‘Agreement Holder’ means the person (whether an individual, a company or other entity) who has entered into the CS agreement as identified in the agreement document (in line with clause 1 of the Terms and Conditions – read Annex 1).
‘Agreement land’ is defined in clause 1 of the Terms and Conditions.
If your application is successful, we will send you an agreement offer letter.
5.1 Entering into an agreement
You can accept or reject the agreement offer – if you accept, you have 3 calendar years to complete capital works from the agreement start date.
If you want to accept the CS Protection and Infrastructure agreement, you must return the signed acceptance declaration to us within 20 working days of the date of the letter. If you do not accept your offer in time, we will withdraw it.
Your agreement cannot start until the Site of Special Scientific Interest (SSSI) consent is granted by Natural England.
The agreement start date will be set out in the agreement document that comes with the agreement offer letter.
Once you have accepted the offer and entered into an agreement, you cannot modify, extend, or amend the agreement without our written permission.
5.2 Evidence: record keeping and site visits
You must keep all records relevant to the expenditure of the grant for at least 7 years from the end of the agreement. The 7-year period starts when each agreement has ended.
All records kept must be dated on or after the agreement start date. We will reject claims and will not pay them if, during a site visit, we find that you ordered or bought items before the start of the agreement or you carried out part or all of the work before, or after, the agreement period.
You must obtain and keep evidence to show that you have carried out all the requirements of your agreement to support your claim or to support a site visit. You must also keep evidence that you are eligible for the scheme.
Your evidence must show that:
- you are eligible for the scheme
- the activities funded under your agreement are appropriate
- the funded activity is taking or has taken place
We need you to do this so that we can demonstrate that public money is being spent effectively and is delivering the intended results.
Record keeping is an important part of an effective farm, or woodland management system. You can use some existing farm records to meet scheme requirements, but you may also need to keep other records specifically about the management being funded.
The record keeping requirements for each capital item are published in the Countryside Stewardship online grants finder tool.
5.2.1 When evidence is required
You must keep any required evidence and supporting documents and have them available on request.
Evidence to support your application
You must keep evidence to show that you, the business, your land, and capital items are eligible as you may have to show this if you are chosen for a site visit.
During the agreement period
You may need to provide evidence to show that you have carried out the required actions. Evidence may be needed:
- to support a claim – more information is set out in the following sections, and where relevant further information will be sent with the claim form covering letter
- during or after an administrative check, site visit, or other checks as described in section 6
After the agreement period
The Terms and Conditions (see Annex 1) explain you must keep all invoices, receipts, accounts, and any other relevant documentation relating to the expenditure of the grant for at least 7 years from the end of the agreement.
5.2.2 General evidence requirements for applicants and agreement holders
It is your responsibility to get all consents, approvals, or permissions that you may need due to your specific circumstances and to carry out the particular capital item. These consents, approvals and permissions must remain effective for the duration of the agreement and you must keep records for 7 years from the end of the agreement.
5.3 Photographic evidence
You need to keep dated photographic evidence for capital items to support an application and any claims. You must make this available when we ask for it, for example as part of administrative record checks or during a site visit.
You must follow the requirements below.
5.3.1 Application stage
You need to take and retain dated photographs showing where works will take place. Your photographs must meet the required standards, explained below.
5.3.2 Claim stage
For a partial or full claim, you must take a dated photograph after the works have been completed and send it with your payment claim. This must show the ‘works completed condition’. The ‘application’ and ‘works completed’ photographs must be taken from the same position.
5.3.3 Photographic evidence quality
All photographs must meet the following standards. Requirements apply equally to digital photographs or those supplied as paper photographs.
Quality – photographs must be in focus and clearly show the relevant capital item or environmental feature. If you send your images by email, please send as JPEG files. Digital images should not be smaller than 600 pixels by 400 pixels and ideally the image file size no larger than 400KB. Printed photographs must be no smaller than 15cm by 10cm. Photographs can be in either portrait or landscape
Photographs must identify the environmental feature or capital item concerned – it is your responsibility to have sufficient evidence that the investment or required management has taken place. For example, more than one photograph may be needed where the feature or capital item exceeds the frame or is not clearly evident from a single photograph.
Where possible, include a significant feature to provide authenticity, for example ditch, fence, farm building, road or telegraph poles.
Where possible, mark the photographed feature location, and direction from which the photograph has been taken, with an ‘X’ and an arrow on a copy of a map (or map extract) of the agreement area.
Where scale or continuity is important, include a feature, or introduce one, for example a quad bike, vehicle or use a sighting pole (2m high with 50cm intervals marked in red and white). Take pictures consistently from the same spot for before and after photographs of the capital item.
5.3.4 Clearly labelled photographs
Use the Ordnance Survey (OS) map sheet reference and National Grid reference for the field parcel where the works are taking place, the implemented capital item code, date, agreement holder name and SBI. If you are sending more than one image, also include the image number.
For example, if we ask you to send ‘before and after’ photographs to support capital items the images should be labelled as OS Ref Capital item code_Date_Name_SBI_Image number.
Save digital images under the label outlined above.
5.4 Publicity requirements
The Terms and Conditions require you to comply with all instructions and guidance relating to acknowledging and publicising the support provided. This includes using any materials or templates which are provided for this purpose.
6. Manage your Protection and Infrastructure grant agreement
You must read and meet the requirements detailed in this section as these are mandatory for all CS Protection and Infrastructure Agreement Holders.
You must only start work (this includes ordering and paying for materials) on or after the agreement start date because we will not pay for materials and work before this date.
You must complete all capital works within 3 years of the agreement start date.
When you have finished the works and you have been charged or invoiced by the contractor or supplier for the items or activities, you can submit your claim. You must keep receipted invoices that show the works have been paid for and provide them on request.
Part claims are allowed in some cases. See section 6.3.
6.1 Agreement period
For applications received after 5 January 2023, the CS Protection and Infrastructure agreement is made up of a 3-year capital grant under which you can apply for support to create FY2 Woodland Infrastructure or Beaver Protection (capital items) BC3, BC4 and BC5.
The agreement runs for a maximum of 3 years from the start date of your agreement. The agreement may not run for the full 3-year period if you finish the works before then.
During this period, you must complete all CS Protection and Infrastructure capital works. You will then have a further 3 months from the end of this period to submit your payment claim.
You must maintain any capital items funded through the scheme in the same condition and specification set out in your agreement for 5 years from the start date of the CS Protection and Infrastructure agreement. This is called the ‘durability’ period of the agreement.
You must also have management control of the land for the length of the CS Protection and Infrastructure agreement including for the 5 years durability period. Section 3.2 explains how this ‘durability’ requirement applies if you are a landlord or a tenant.
6.2 Change in circumstances
You must notify us as soon as you can if there is a change in your circumstances that might:
- affect the amount of funding you have been or will be paid
- prevent you from complying with the conditions of your agreement
- prevent you from carrying out the work set out in your agreement, including preventing you from carrying out the work to the agreed standard or in the agreed timeframe
- affect your continued entitlement to agreement funding, for example if you no longer have management control of the land parcels included in your agreement
6.3 Amendments
You should be able to carry out the capital items under your agreement without difficulty. However, should an exceptional situation arise where you need to change the items or their time schedule, you can ask us to amend your agreement. We will only agree to changes that are necessary to achieve the objectives of the scheme.
You need written permission from us before you can amend or reschedule approved capital items. You should contact us if you would like to discuss an amendment to your agreement before the end of the original agreement period to complete the capital items.
We must agree to the request before you make any changes to the item, its location, or timing, and you may need to repay all or part of previous payments that you have received.
We will write to confirm if your request is successful. The amendment will not be valid until you have received written confirmation from us agreeing to the amendment and advising you of the date from which it will take effect.
6.4 Requirements when using own labour or contractors for capital works
6.4.1 Using own labour for capital works
You can use your own labour or a farm employee’s labour to carry out capital works. If you do so, you will need to prepare time sheets signed by the employee and employer showing all of the following:
- the hourly rate for your labour or a farm employee’s labour
- what work was carried out
- the date the work was done
You must tell the employee(s) about the agreement and its requirements. It is your responsibility to make sure that work carried out using your own labour or a farm employee’s labour, does not breach the terms of your agreement. If the employee commits any breaches, you will be responsible for any payment reductions.
For FY2 Woodland Infrastructure we will pay 40% of actual costs (including VAT and agent’s fees, where applicable). If you are using your own labour to complete this item, we will pay 80% of the 40% value.
6.4.2 Using contractors to carry out capital works
You can employ contractors to carry out the work needed for the capital items. You must tell the contractor about the agreement and its requirements. It is your responsibility to make sure that work carried out by contractors does not breach the terms of your agreement. If the contractor commits any breaches, you will be responsible for any payment reductions.
6.4.3 Using a licenced beaver manager for capital works
A licenced beaver manager must carry out any capital works required for BC5 Expert dam management. The works must be agreed with Natural England.
6.5 Make a claim for payment
CS Protection and Infrastructure grants agreements include a 3-year programme of capital works.
When you have finished the works and you have been charged or invoiced by the contractor or supplier for the items or activities, you can submit your claim for payment. The minimum claim value is £500. You can submit a claim for payment at any time of the year. We will pay valid claims within 2 months of receiving them.
If you are making interim (multiple) claims, the minimum claim value of £500 does not apply to your final claim.
We must receive all claims for payment no later than 3 months after the agreement end date. If we receive a claim more than 3 months but less than 6 months after the agreement end date, a late claim reduction will be applied. If we receive a claim more than 6 months after the agreement end date, the claim will not be accepted and no payment will be made.
6.5.1. Submitting claims
Once the capital works are finished and you have been charged or invoiced by the contractor or supplier, you can sign into the Rural Payments service and submit a claim online.
You can read more about how to submit a capital claim online.
If you cannot make a claim online contact us to ask for a claim form.
Rural Payments Agency (CS)
PO Box 324
Worksop
S95 1DF
Email: [email protected]
Telephone: 03000 200 301
Monday to Friday, 8:30am to 5pm, except bank holidays
Find out about call charges
You must keep evidence to show that the work is finished. Section 6.4 explains the photographic evidence you need and what evidence is needed for individual capital items.
You may need to submit necessary consents or permissions with your claim, or you may need to supply them on request. See the individual capital item specifications for details.
As the agreement holder, you must keep the completed items to the condition and specification for which the aid was granted for 5 years from the start date of the agreement. This is a requirement of the agreement.
This also applies to landlords where management of the agreement land reverts from the tenant agreement holder to the countersigning landlord during the durability period (read section 3.3 in the applicant’s guide).
6.6 Scheme checks and site visits
We are required to make sure that CS is properly controlled, to protect public money. Site visits are carried out to monitor Agreement Holder compliance with the rules governing their agreements and the success of CS overall. They focus on assessing how the environmental aims are being delivered.
We will check that advice and guidance have been followed and if we think there is an issue that can be resolved, we will offer further advice and guidance, or we may deal with any agreement breaches or non-compliances we find in line with section 6.5 of this manual and the terms and conditions.
We carry out a number of checks on claims:
- administrative record checks
- in situ visits
- agreement monitoring visits
- physical or virtual site visits
You must allow any UK public authority (or their authorised representatives or auditors) to access your land or premises to carry out site visits.
We will seek to agree a date and time for a site visit where possible. If not, you will be notified at least 48 hours in advance of the site visit unless we have reasons to suspect that you are in breach of your agreement.
You must help and co-operate with any person carrying out a site visit (including controls and spot-checks) and shall provide access to any land, premises, plant, equipment, or documents which may be required. Any refusal to do so or obstruction will be treated as a breach of the CS Terms and Conditions, and you may face recovery, suspension or termination of your agreement. We may also refuse support for other Defra grant schemes for up to 2 years.
6.6.1 Administrative record checks
We will check all stages of your application and claims, including your application form, claim forms and the nature and quality of any supporting evidence we ask you to send us, such as receipts and farm records. This is to make sure that you meet eligibility requirements at the application stage, and that various forms and records match up during the whole agreement period.
If you do not provide records when asked, or there are discrepancies, we will treat this as a breach of your agreement.
6.6.2 In situ visits
As part of our administrative checks, we may make focused visual checks of your holding, targeted at specific capital items. These visits may include record checks.
6.6.3 Agreement monitoring visits
Advisers may visit sites to monitor environmental progress, discuss site reports, or if you ask us to visit.
6.6.4 Site visits
Each year we will carry out site visits on a sample of agreements to make sure scheme requirements have been met. If we find a breach of the rules, we may apply reductions (read section 6.5).
Find out what to expect from a site visit.
6.6.5 Refusal or withdrawal of support
In certain cases, we may refuse, or withdraw in full, the support claimed and terminate your existing agreement. We will do this if we think any of the following has happened:
- you have committed a serious non-compliance
- you have provided false evidence
- you have negligently failed to provide the necessary information (for instance, where we have asked for it repeatedly and there is no good reason why you have not provided it)
If we have to withdraw support for these reasons, we will terminate the existing agreement and you will not be permitted to re-apply for the scheme or to other Defra grant schemes for 2 years.
We may also refuse support for other Defra grant schemes for up to 2 years. If this is the case, we will tell you and you will have the right to appeal against this decision.
6.6.6 Cross compliance
You must comply with all applicable domestic law. In particular, note that while cross compliance no longer applies, the majority of cross compliance rules are also requirements under domestic legislation.
6.7 What happens if you breach your agreement
If you do not meet the terms of your agreement, we may reduce or withhold your payment or ask you to repay any monies we have already paid to you.
If we find a breach, we will write to you and tell you. You’ll have the opportunity to appeal if you do not agree with our findings. If a breach is confirmed, we’ll work out the most appropriate action we need to take and let you know. We may apply more than one course of action depending on the breach found. We’ll assess the level of breach in a fair and consistent manner, on a case-by-case basis, using the following set of criteria:
- to what extent the breach can be rectified
- the circumstances, nature and consequences surrounding the breach
- any failure to cooperate with site visits, or further investigations
- any steps taken to report a change in circumstances
- whether it is an isolated or a repeat occurrence
- whether it was intentional
- whether it was because of reckless of negligent action
If there’s a breach of your agreement or the regulations, we may:
- ask you to correct the breach
- issue a letter explaining that we’ve assessed the breach and what you have to do to amend your agreement
For more serious breaches, we may:
- reduce the payments you get, or withhold part of them
- reduce or withhold money from other schemes
- recover money we’ve already paid
In the most extreme cases, we may:
- end your agreement
- stop you receiving financial assistance (other than BPS) under any other scheme for up to 2 years
In exceptional circumstances where there is reasonable suspicion of a serious breach or fraud, then we may access land and your premises without notice, using powers of entry. In these circumstances, for example as part of a fraud investigation, we may access any computer that’s been used in connection with the evidence or these records.
If we find breaches during administrative checks or any site visits, we will write to tell you and you will have the opportunity to make written representations if you feel that our findings are incorrect.
In these cases, we will work out the level of reduction we need to apply, by looking at the severity of the breach and whether it is an isolated or a repeat occurrence. We may apply a reduction to your claims, unless you can demonstrate you were compliant.
A brief explanation of how breaches are assessed is set out below.
6.7.1 Severity
We will assess what has happened due to the breach/non-compliance and consider the objectives of the agreement or specifications that were not met. For example, constructing an item in a way that does not deliver what the item was designed for would be classed as a severe breach. As part of this assessment, we will also take into account whether the breach will have short or long-term impacts.
6.7.2 Re-occurrence
The assessment will depend on a number of factors, for example whether a similar event of non- compliance has been found on previous claims and whether the re-occurrence concerns the same or a similar type of work.
If we consider that a breach is so serious that it cannot be rectified, we may have to cancel the agreement. In serious circumstances, you may be forbidden from entering another agri-environment scheme for up to 2 years.
6.7.3 Over-declaration of expenditure
If you submit a claim for more than the value of the costs which are eligible to be claimed, we will reduce the payment to the correct amount, or recover the amount of over-declaration if payment has already been made.
6.8 Good reasons for a breach
You may be unable to meet your requirements under the agreement because of exceptional circumstances. If this happens, you must write to tell us, within 8 weeks from the date on which you (or any person authorised to act for you) are able to do so. You will need to provide written evidence to show:
- what has happened
- how the event meant you were unable to meet the scheme rules
Good reasons for a breach may include, but are not limited to:
- the death of the agreement holder
- serious illness
- a severe weather event
- the accidental destruction of capital items connected to your agreement
- damage caused by criminality
- supply chain issues
- an epizootic or a plant disease affecting part or all of your crops, trees, or livestock
We will consider the facts to decide whether or not the agreement holder is relieved of all or part of their obligations under the agreement, and whether all or part of the grant should be withheld or repaid.
If you are aware of the issue when entering into your agreement then it is unlikely to be considered a good reason for a breach.
6.9 Change of ownership
You cannot transfer your agreement during the 3-year agreement period. This rule applies only during the 3-year period from the start of your agreement (not the 5-year requirement to keep capital items funded through the scheme).
If you sell or let, all or part of the land under your CS Protection and Infrastructure agreement to another party, we will end your agreement on those parcels. You may need to repay all or some of the grant payments you have already received.
If, after completing your CS Protection and Infrastructure agreement, you sell or let all or part of the land previously under your agreement to another party during the subsequent durability period, you may need to repay part of the grant payments you have already received.
6.10 Disputes, appeals and complaints
If you’re unhappy with a decision we have taken about your application or agreement, you can submit a complaint.
If you’re unhappy with a decision we’ve taken or service you’ve had from us, you can ask us to reconsider. If you’re still unhappy with the result of our decision, you can appeal.
Follow the RPA complaints procedure to raise a complaint. This also includes information on how to request a reconsideration or submit an appeal.