Advice on indicative standards of operation and environmental performance for industrial sectors.

Documents

Sector Guidance Note S5.06: recovery and disposal of hazardous and non-hazardous waste

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Treating waste by thermal desorption: addendum to S5.06

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Guidance for the storage and treatment of aerosol canisters and similar packaged wastes: addendum to S5.06

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

Operators of waste activities that need permits must meet the requirements of:

These are the initial points for defining appropriate measures and best available techniques (BAT).

New waste installations and new or replacement plant at existing waste installations must use BAT and meet associated emission limits from the date they are first permitted.

BAT and associated emission limits are set out in Commission Implementing Decision (EU) 2018/1147 on the European IPPC Bureau website.

For existing waste installations, operators will need to make sure that the BAT conclusions are met in full by August 2022.

Updates to this page

Published 13 May 2013
Last updated 10 October 2018 + show all updates
  1. Operators of waste activities that need permits must meet the requirements of S5.06, clinical waste guidance S5.07 and the waste treatments BREF.

  2. Page updated: New waste installations and new or replacement plant at existing waste installations must use best available techniques (BAT) and meet associated emission limits from the date they are first permitted. In all other cases the Environment Agency will work with the operators of existing waste installations to ensure that the BAT conclusions are met in full by August 2022.

  3. First published.

Sign up for emails or print this page