Standard rules for temporary scaffolding affecting up to 20 metres length of a main river.

Applies to England

Documents

SR2015 No 34: temporary scaffolding affecting up to 20 metres of a main river

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Generic risk assessment for SR2015 No 34

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

These rules allow you to erect and use temporary scaffolding affecting up to 20 metres length of a main river for a maximum of 8 weeks.

These rules do not allow you to erect or use scaffolding:

  • on or within 8 metres of flood defences
  • during the fish breeding season

Updates to this page

Published 6 April 2016
Last updated 31 July 2019 + show all updates
  1. Updated operational conditions and screening distances associated with each standard rule. The aim of this is to improve the uptake of flood risk standard rules permits.