Guidance

The statutory consents regime for overhead power lines in England and Wales: guidance note

An outline of the statutory consenting process in England and Wales under section 37 of the Electricity Act 1989 to install and keep installed electric lines above ground (“overhead lines”).

Documents

The statutory consents regime for overhead power lines in England and Wales under Section 37 of the Electricity Act 1989: guidance note

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

An outline of the statutory consenting process in England and Wales under section 37 of the Electricity Act 1989 to install and keep installed electric lines above ground (“overhead lines”).

Updates to this page

Published 1 July 2014

Sign up for emails or print this page