Overhead lines: applying for consent

Guidance on obtaining consent for development of energy infrastructure: overhead lines.

Consents for the construction of overhead lines with a nominal voltage of less than 132 kilovolts or that are less than 2 kilometres in length are regulated by the Department for Energy Security and Net Zero (DESNZ) under the provisions of section 37 of the Electricity Act 1989.

Development consent is needed for all but the most minor lines in England and Wales - see The Overhead Lines (Exemption) (England and Wales) Regulations 2009.

The Planning Act 2008 regulates development consent for Nationally Significant Infrastructure Projects (NSIPs) and the threshold set in the Planning Act 2008 for Overhead Lines is for applications for lines with a nominal voltage capacity of 132 kilovolts or greater and more than 2 kilometres in length.

The UK Energy Portal

The UK Energy Portal processes applications for consent under the Electricity Act 1989 for overhead power lines and necessary wayleaves.

Sign in to the Portal

Statutory Consents Regime for Overhead Power Lines

Guidance Note - The Statutory Consents Regime for Overhead Power Lines in England and Wales under Section 37 of the Electricity Act 1989

This guidance provides:

  • an outline of the statutory consenting process in England and Wales under section 37 of the Electricity Act 1989 to install and keep installed electric lines above ground (‘overhead lines’)
  • guidance on thresholds and application fees
  • it replaces guidance previously contained in Joint Circular 14/90 for section 37 applications in England and Wales which has been cancelled by the Ministry of Housing, Communities and Local Government
  • the application fees in this document have been updated as in following section

Fees

Fees for applications for overhead lines in England and Wales under section 37 of the Electricity Act 1989 are implemented by The Electricity (Applications for Consent) Amendment (England and Wales) Regulations 2013.

Revised fees were introduced from 6 April 2017 by The Electricity (Applications for Consent)(Amendment)(England and Wales) Regulations 2017.

Fees payable

The fees payable from 6 April 2017 are:

Line capacity Cost
Overhead line with a nominal capacity not exceeding 132kV £402.50
Overhead line with a nominal capacity exceeding 132kV £902.50
Environmental Impact Assessment (EIA) Development application (additional fee) £375
Screening opinion fee payable to the Secretary of State £60

The additional fee for an application that is EIA development reflects the scale, complexity and/or sensitive location of those applications and includes costs for a specialist Environmental Adviser to assess the Environmental Statement.

Electromagnetic fields (EMFs) and power lines

The government published a response on 16 October 2009 to the Stakeholder Advisory Group on Extremely Low Frequency Electromagnetic Fields (SAGE) First Interim Assessment: Power Lines and Property, Wiring in Homes and Electrical Equipment in Homes:

Read the government response and Written Ministerial Statement

To implement the department’s actions to the SAGE First Interim Assessment, the following voluntary Codes of Practice were introduced in England, Wales, Scotland and Northern Ireland:

1. Optimum phasing of high voltage double-circuit power lines: a voluntary code of practice (March 2012)

This Code of Practice provides that industry will report to government on the prevalence of optimum phasing at 3 year intervals.

2. Power lines: demonstrating compliance with EMF public exposure guidelines: a voluntary code of practice March 2012

3. Power lines: control of microshocks and other indirect effects of public exposure to electric fields: a voluntary code of practice, July 2013

On 21 October 2011 the Department of Health published its response to the SAGE Second Assessment: Electricity Distribution (including low-voltage and intermediate voltage circuits and substations) and Report on Discussions on Science (‘SAGE2’).

The Department asked the electricity industry to undertake some work in order to fulfil the SAGE 2 recommendations in regard to measures relating to low voltage distribution networks and substations. In response, the Energy Networks Association published Engineering Recommendation G92: guidelines for best practice in relation to electric and magnetic fields (EMFs) in the design and management of low voltage networks.

Processing

Applications for consent must comply with:

The Guidance Note The Statutory Consents Regime for Overhead Power Lines in England and Wales under Section 37 of the Electricity Act 1989 provides further information.

Environmental Impact Assessments (EIAs)

The department must consider the environmental consequences of all applications.

Key regulations include:

As a public body, the department also has wider duties to promote biodiversity and ensure public participation in its decision-making.

EIA screening decisions on overhead line applications

The Secretary of State makes screening decisions on applications relating to overhead lines. The details of individual screening decisions are available at:

Public inquiries

Local Planning Authorities have the right to object to an application, and if that objection cannot be overcome by the applicant or addressed by an appropriate planning condition, the Secretary of State is obliged to arrange for a public inquiry to be held.

Inquiries are held under the provisions of The Electricity Generating Stations and Overhead Lines (Inquiries Procedure) (England and Wales) Rules 2007.

Further guidance: The Electricity Generating Stations and Overhead Lines (Inquiries Procedure) (England and Wales) Rules 2007: guidance for participants.

Compulsory purchase orders

In accordance with Schedule 3 to the Electricity Act 1989 compulsory purchase powers can be used by statutory undertakers to acquire land or rights over land for the installation and retention of electric lines. Compulsory purchase is intended as a last resort to secure the assembly of all the land needed for the implementation of projects. Compulsory Purchase Orders should only be made where there is a compelling case in the public interest to do so. In such cases, the developer (also known as the Acquiring Authority) will make an Order and then seek confirmation of that Order from the Secretary of State. Where statutory objections are raised (i.e. objections from owners, lessees and occupiers) the Secretary of State is required to hold a public inquiry before a decision can be made on the Order.

Public inquiries in England and Wales relating to electricity infrastructure are held in accordance with:

Where the Compulsory Purchase Order relates to Statutory undertakers’ land, please refer to Section 16 or Section 31 of the Acquisition of Land Act 1981. The Ministry of Housing, Communities and Local Government has produced guidance on compulsory purchase procedures for England only.

Contact

[email protected]

Updates to this page

Published 1 January 2000
Last updated 19 October 2022 + show all updates
  1. The contact email address is now [email protected].

  2. Screening decision on upgrade to overhead line at Upton Hall Farm, Lythe added.

  3. Screen decision on new overhead line, Beacon Farm, Whitby added.

  4. New screening decision added.

  5. Added 3 recent screening decisions for overhead electricity lines.

  6. Added 3 recent screening decisions for electricity lines.

  7. Overhead electricity line (ZZA IAMP) diversion: screening decision added.

  8. First published.