Section 62A Planning Application: S62A/22/0000004 Land east of Parsonage Road, and south of Hall Road, Stansted, Essex, CM22 6PL
Overview of case details, documents, key dates and how to make a representation.
Applies to England
Type of application
Full Planning Application
Applicant name
Stansted Airport Limited (‘STAL’)
Site address
Land east of Parsonage Road, and south of Hall Road, Stansted, Essex, CM22 6PL
Description of proposed development
The erection of a 14.3 MW solar photovoltaic farm with associated access tracks, landscaping, supplementary battery storage, and associated infrastructure.
Case Office
Major Casework Team
Procedure
Hearing
Key dates:
Date | |
---|---|
Date application valid | 1 June 2022 |
Date by when representations must be made | 7 July 2022 |
Hearing date and venue | 10.00am on 9 August 2022 at Council Chamber, London Road, Saffron Walden, CB11 4ER |
Decision date | 24 August 2022 |
Hearing Documents
Decision
Make a representation
The application can be inspected under the application plans and documents heading below.
You will be able to comment on this application until 7 July 2022
Please base your comments on planning matters.
Please avoid the use of inflammatory, discriminatory or abusive comments
All representations made in connection with the development proposal will be made publicly available on the website shortly after the end of the representation period. The name of the individual author or organisation will be published however addresses, signatures and contact details will not be published. We advise you not to include any other personal information about yourself or others.
Our Customer Privacy Notice sets out how we handle personal data in accordance with the law.
Send your comments via email to [email protected]
or write to
The Planning Inspectorate,
Major Casework Team,
Room 3J Kite Wing,
Temple Quay House,
2 The Square, Bristol,
BS1 6PN
Please include the application reference number and site address.
This application will be determined by an Inspector appointed by the Secretary of State. Shortly after the close of the representation period the Planning Inspectorate will consider whether a hearing is necessary. In the event that a hearing is scheduled, and you would wish to speak at the hearing, you must make this request at the time you submit your written representations.
Where the application is to be considered at a hearing, notice of the date, time and venue for the hearing along with the name of the person holding the hearing, will be published on this website at least two weeks before the date of the hearing.
Application Plans and Documents
Documents received from the applicant on 19 and 20 July 2022
Questionnaire and supporting documents
Comments
Consultees
Interested Parties
Comments received after the Hearing
Planning Inspectorate Correspondence
Updates to this page
Published 6 June 2022Last updated 24 August 2022 + show all updates
-
Decision notice and statement of reasons dated 24 August 2022
-
4 new documents under Comments received after the Hearing heading
-
Jack Coleman document added
-
Essex County Council Highways reconsultation response 29 July 2022, Issues Report, Draft conditions and Agenda documents published
-
Hearing notification updated
-
NATS 2nd response, National Highways 2nd response, Site Location & Land Ownership Plan, and Essex County Council - Lead Local Flood Authority 2nd response
-
UDC draft committee meeting minutes from 6 July 2022 and hearing notice updated
-
Historic England 2nd response document published
-
Documents received from the applicant on 19 and 20 July 2022 published and hearing information added
-
ECC Energy and Low Carbon consultation response (reissued) document published
-
ECC GL response, 399662 Consultation Response and Annex A to standard letters – May 2022 documents published
-
Letter to applicant dated 11 July from the Planning Inspectorate published
-
Affinity Water Ltd, ECC Energy & Low Carbon and ECC Highways consultation documents added
-
MAG Response 2022-132 and PINS Letter S62A documents added
-
Takeley Parish Council document added
-
Essex County Council Development and Flood Risk document added
-
Historic England document added
-
Environment Agency and Essex County Council Historic Environment Consultant documents added
-
New document from National Highways published under 'Consultees'.
-
Consultees documents added
-
Planning Inspectorate to the applicant and the response - 8 June 2022 document added
-
Additional application documents added to case information
-
New documents published under 'Questionnaire and Supporting Documents' and 'Planning Inspectorate Correspondence'
-
First published.